(Jun 30,2011)(Announcement)Status of flood prevention measures from tsunami at Kashiwazaki Kariwa Nuclear Power Station
(Jun 30,2011)Status of Evaluation work of TEPCO employees' Exposure Dose at Fukushima Daiichi Nuclear Power Station (3rd release)
(Jun 30,2011)Enhancement and Strengthening of Medical System of Fukushima Daiichi Nuclear Power Station (Opening of Emergency Medical Treatment Room)
(Jun 30,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 30)
(Jun 30,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 30)
(Jun 30,2011)Future Operation of Unit 7, Kashiwazaki Kariwa Nuclear Power Station
(Jun 30,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (97 release)
(Jun 30,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (99th release)
(Jun 30,2011)Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 30)
(Jun 30,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 29)
(Jun 30,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 30,2011)Regarding the Preventive Measures against the Causes of Incompatibility of Environmental Monitoring when Opening the Airlock at Fukushima Daiichi Nuclear Power Station Unit 2
(Jun 30,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 30)
(Jun 30,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 30)
(Jun 30,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 30)
(Jun 29,2011)Improvement plan for the exact nuclide analysis at the site of Fukushima Daiichi Nuclear Power Station under instruction of NISA (Continued report 6)
(Jun 29,2011)Situation of storing and treatment of accumulated water including highly concentrated radioactive materials at Fukushima Daiichi Nuclear Power Station(1st Release)
(Jun 29,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 29)
(Jun 29,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 29)
(Jun 29,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 29)
(Jun 29,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (98th release)
(Jun 29,2011)The results of nuclide analyses of radioactive materials in the ocean soil off the coast of Fukushima Daiichi Nuclear Power Station (continued report 4)
(Jun 29,2011)Fuel Cost Adjustment in Electricity Fees for August 2011
(Jun 29,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 28)
(Jun 29,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (96 release)
(Jun 29,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 pm, June 29)
(Jun 29,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 29)
(Jun 28,2011)Announcement of Change of Directors
(Jun 28,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 28)
(Jun 28,2011)Strengthening Organization of "Fukushima Nuclear Influence Response Division"
(Jun 28,2011)Personnel Revision
(Jun 28,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 28)
(Jun 28,2011)Implementation of injection of nitrogen into Primary Containment Vessel of Unit 2 at Fukushima Daiichi Nuclear Power Station
(Jun 28,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued report 10)
(Jun 28,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 28,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 27)
(Jun 28,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (97th release)
(Jun 28,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (95 release)
(Jun 28,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 28)
(Jun 28,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 28)
(Jun 28,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 28)
(Jun 27,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 27)
(Jun 27,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 26)
(Jun 27,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (96th release)
(Jun 27,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (94th release)
(Jun 27,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 27)
(Jun 27,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 27)
(Jun 27,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 27)
(Jun 27,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 pm, June 27)
(Jun 26,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 26)
(Jun 26,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (95th release)
(Jun 26,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (95th release)
(Jun 26,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 26)
(Jun 26,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (93rd release)
(Jun 26,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 26)
(Jun 26,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 26)
(Jun 26,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 26)
(Jun 25,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 25)
(Jun 25,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (20th release)
(Jun 25,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 15:00 PM, June 25)
(Jun 25,2011)The results of nuclide analyses of radioactive materials in the ocean soil off the coast of Fukushima Daiichi Nuclear Power Station (continued report 3)
(Jun 25,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 25,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Miyagi Prefecture
(Jun 25,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 24)
(Jun 25,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (92nd release)
(Jun 25,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (94th release)
(Jun 25,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 15:00 pm, June 25)
(Jun 25,2011)Regarding the receipt of the order to submit reports related to the injection of nitrogen to the reactor containment vessel of Unit 2 at Fukushima Daiichi Nuclear Power Station
(Jun 25,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 25)
(Jun 25,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 25)
(Jun 24,2011)Regarding the report on installing the Reactor Building Cover for Unit 1 of Fukushima Daiichi Nuclear Power Station
(Jun 24,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 24)
(Jun 24,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 24)
(Jun 24,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 24)
(Jun 24,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (93rd release)
(Jun 24,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 23)
(Jun 24,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 24,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (91st release)
(Jun 24,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued report 9)
(Jun 24,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 24)
(Jun 24,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 24)
(Jun 23,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (90th release)
(Jun 23,2011)Detection of slight amount of radioactive materials by periodic radioactivity measurement at Kashiwazaki Kariwa Nuclear Power Station (update)
(Jun 23,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 23)
(Jun 23,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 23)
(Jun 23,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 23)
(Jun 23,2011)The results of nuclide analyses of radioactive materials in the ocean soil off the coast of Fukushima Daiichi Nuclear Power Station (continued report)
(Jun 23,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 23,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 22)
(Jun 23,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (92th release)
(Jun 23,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 23)
(Jun 23,2011)Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 23)
(Jun 23,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 23)
(Jun 22,2011)Notice for modifying partly Brief note on the settlement of accounts ending in March 2011 (consolidated, Japanese standard)" due to the occurrence of subsequent events (Modified)"
(Jun 22,2011)Instruction to report on installing the reactor building cover for Unit 1
(Jun 22,2011)Regarding the receipt of the order to submit reports related to Injection of nitrogen to the reactor containment vessel of Unit 2 at Fukushima Daiichi Nuclear Power Station
(Jun 22,2011)Submission of Report regarding Transfer of High Level Radioactive Water in Fukushima Daiichi Nuclear Power Station to the Centralized Radiation Waste Treatment Facility
(Jun 22,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 22)
(Jun 22,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 22)
(Jun 22,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (91th release)
(Jun 22,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (19th release)
(Jun 22,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 21)
(Jun 22,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (89th release)
(Jun 22,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 22)
(Jun 22,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 22)
(Jun 22,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 22)
(Jun 21,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 21)
(Jun 21,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 21)
(Jun 21,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 21)
(Jun 21,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (90th release)
(Jun 21,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued report 8)
(Jun 21,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 20)
(Jun 21,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 21,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (88th release)
(Jun 21,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 21)
(Jun 21,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 21)
(Jun 20,2011)Evaluation Status of Site Workers' Exposure Doses during Emergency Work at Fukushima Daiichi Nuclear Power Station (Continued Report 2)
(Jun 20,2011)Status of Evaluation work of TEPCO employees' Exposure Dose at Fukushima Daiichi Nuclear Power Station (2nd release)
(Jun 20,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 20)
(Jun 20,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (89th release)
(Jun 20,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 20)
(Jun 20,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (87th release)
(Jun 20,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 19)
(Jun 20,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 20)
(Jun 20,2011)Incorrect calculation of delay interest on the electricity bill
(Jun 20,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 20)
(Jun 20,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 20)
(Jun 19,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 19)
(Jun 19,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 19)
(Jun 19,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 19)
(Jun 19,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (88th release)
(Jun 19,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (86th release)
(Jun 19,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 18)
(Jun 19,2011)Regarding improvements to work environment inside the Reactor Building of Unit 2 and opening the airlock at Fukushima Daiichi Nuclear Power Station
(Jun 19,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 19)
(Jun 19,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 19)
(Jun 18,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (87th release)
(Jun 18,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 18,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 17)
(Jun 18,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (85th release)
(Jun 18,2011)Improvement plan for the exact nuclide analysis at the site of Fukushima Daiichi Nuclear Power Station under instruction of NISA (Continued report 5)
(Jun 18,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 18)
(Jun 18,2011)First Response at Tohoku Chihou Taiheiyou Oki Earthquake in Fukushima Daiichi Nuclear Power Station
(Jun 18,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 18)
(Jun 18,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 18)
(Jun 18,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 18)
(Jun 18,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 18)
(Jun 17,2011)Submission of reports to NISA regarding results of earthquake response analysis using observed seismic data collected at Fukushima Daiichi Nuclear Power Station during the Tohoku-Taiheiyou-Oki Earthquake, etc.
(Jun 17,2011)The Report to NISA on cause analysis on exposure of radiation workers exceeding dose limit and development of measures on recurrence prevention at emergency work in Fukushima Daiichi Nuclear Power Station
(Jun 17,2011)Submission of Report regarding Transfer of High Level Radioactive Water in Fukushima Daiichi Nuclear Power Station to the Centralized Radiation Waste Treatment Facility
(Jun 17,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued 7)
(Jun 17,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 17)
(Jun 17,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 17)
(Jun 17,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 17)
(Jun 17,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (84th release)
(Jun 17,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (86th release)
(Jun 17,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 16)
(Jun 17,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 17)
(Jun 17,2011)Progress status of the Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station""
(Jun 17,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 17)
(Jun 16,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 16)
(Jun 16,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 16)
(Jun 16,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 15)
(Jun 16,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (85th release)
(Jun 16,2011)Regarding the receipt of the order to submit reports related to Improvements to work environment inside the Reactor Building of Unit 2 at Fukushima Daiichi Nuclear Power Station
(Jun 16,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 16,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (83rd release)
(Jun 16,2011)Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 16)
(Jun 16,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 16)
(Jun 16,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 16)
(Jun 16,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 16)
(Jun 15,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 15)
(Jun 15,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 15)
(Jun 15,2011)Regarding the report to NISA with regards to the Installation of alternative cooling and purification system of spent fuel pool of Unit 3 of Fukushima Daiichi Nuclear Power Station
(Jun 15,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (18th release)
(Jun 15,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 14)
(Jun 15,2011)Submission of report to NISA regarding implementation of necessary measures on fire prevention in relation to overhang-type high-voltage breakers at nuclear power stations
(Jun 15,2011)Error alarm generation in emergency air-conditioning units of Unit 7 in operation
(Jun 15,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (84th release)
(Jun 15,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (82nd release)
(Jun 15,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 15)
(Jun 15,2011)Investigation results of oil leakage at the sea surface around the water discharge canal of Units 3 and 4, Fukushima Daini Nuclear Power Station
(Jun 15,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 15)
(Jun 15,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 15)
(Jun 14,2011)Outline of the reactor building covering plan and commencement of main construction of Unit 1 at Fukushima Daiichi Nuclear Power Station
(Jun 14,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (83rd release)
(Jun 14,2011)Detection of slight amount of radioactive materials by periodic radioactivity measurement at Kashiwazaki Kariwa Nuclear Power Station (update)<Measurement results of milk and evaluation>
(Jun 14,2011)Submission of the report regarding implementation of countermeasures against severe accidents based on the accident in Fukushima Daiichi Nuclear Power Station to Nuclear and Industrial Safety Agency, Ministry of Economy, Trade and Industry
(Jun 14,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued 6)
(Jun 14,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (81st release)
(Jun 14,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 13)
(Jun 14,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 14,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 pM, June 14)
(Jun 14,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 14)
(Jun 14,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (17th release)
(Jun 14,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 14)
(Jun 14,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 14)
(Jun 14,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 14)
(Jun 14,2011)The president's comments concerning the announcement of Cabinet approval of the Nuclear Disaster Compensation Bill
(Jun 13,2011)Correction of parameters related to the plants in Fukushima Daiichi Nuclear Power Station
(Jun 13,2011)Evaluation Status of Site Workers' Exposure Doses during Emergency Work at Fukushima Daiichi Nuclear Power Station
(Jun 13,2011)Regarding the receipt of the direction in relation to the submission of the report with regards to the Installation of alternative cooling and purification system of spent fuel pool of Unit 3 of Fukushima Daiichi Nuclear Power Station
(Jun 13,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 13)
(Jun 13,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 13)
(Jun 13,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (82nd release)
(Jun 13,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 12)
(Jun 13,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (80th release)
(Jun 13,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 13)
(Jun 13,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 Am, June 13)
(Jun 13,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 13)
(Jun 12,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 12,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 11)
(Jun 12,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquak(as of 3:00 PM, June 12)
(Jun 12,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (81th release)
(Jun 12,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (79th release)
(Jun 12,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 12)
(Jun 12,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 12)
(Jun 12,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 12)
(Jun 12,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 12)
(Jun 11,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 11)
(Jun 11,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 10)
(Jun 11,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 11)
(Jun 11,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 11,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (80th release)
(Jun 11,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (16th release)
(Jun 11,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (78th release)
(Jun 11,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 11)
(Jun 11,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 11)
(Jun 11,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 11)
(Jun 10,2011)Receipt of instruction document from NISA on cause analysis on exposure of radiation workers exceeding dose limit and development of measures on recurrence prevention at emergency work in Fukushima Daiichi Nuclear Power Station
(Jun 10,2011)Status of improvement on working environment of workers in Fukushima Daiichi Nuclear Power Station
(Jun 10,2011)Status of Evaluation work of TEPCO employees' Exposure Dose at Fukushima Daiichi Nuclear Power Station (Continued Releases)
(Jun 10,2011)Establishment of "Fukushima Nuclear Accidents Investigation Committee" inside TEPCO and "Nuclear Safety and Quality Assurance Meeting Accident Investigation Verification Committee"
(Jun 10,2011)Survey result of fire at the Reactor Building Annex Area, Unit 1, Fukushima Daini Nuclear Power Station
(Jun 10,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued 5)
(Jun 10,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (79th release)
(Jun 10,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (77th release)
(Jun 10,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 9)
(Jun 10,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 10)
(Jun 10,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 10)
(Jun 10,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 10)
(Jun 10,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 10)
(Jun 10,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 10)
(Jun 9,2011)Request for conserving electricity to customers upon start of "Electricity Forecast"
(Jun 9,2011)Commencement of active test of treatment facility and storing facility of water including highly concentrated radioactive materials at Fukushima Daiichi Nuclear Power Station and Receipt of instruction document regarding installment of treatment facility and storing facility of water including highly concentrated radioactive materials
(Jun 9,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 9)
(Jun 9,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (78th release)
(Jun 9,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 9,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 8)
(Jun 9,2011)A report on installment of treatment facility and storing facility of water including highly concentrated radioactive materials at Fukushima Daiichi Nuclear Power Station to Nuclear and Industrial Safety Agency of Ministry of Economy, Trade and Industry
(Jun 9,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (76th release)
(Jun 9,2011)Confirmed oil leakage at sea surface around the water discharge canal of Units 3 and 4, Fukushima Daini Nuclear Power Station (continued report)
(Jun 9,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 9)
(Jun 9,2011)Submission of the report regarding inspection of protection equipments of transmission lines at substations, etc. to Nuclear and Industrial Safety Agency, Ministry of Economy, Trade and Industry
(Jun 9,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 9)
(Jun 9,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 9)
(Jun 9,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 9)
(Jun 9,2011)Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 9)
(Jun 8,2011)Regarding the receipt of the order to submit reports related to Improvements to work environment inside the Reactor Building of Unit 2 at Fukushima Daiichi Nuclear Power Station
(Jun 8,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (75th release)
(Jun 8,2011)Regarding the result of investigation in relation to the undisclosed monitoring data at Fukushima Daiichi Nuclear Power Station
(Jun 8,2011)Submission of the Report on Transfer of High Level Radioactive Wastewater Accumulated in the Fukushima Daiichi Nuclear Power Station to the Centralized Radiation Waste Treatment Facility
(Jun 8,2011)Oil leakage to the sea confirmed around the water discharge canal of Unit 3 and 4, Fukushima Daini Nuclear Power Station
(Jun 8,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 8)
(Jun 8,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 8)
(Jun 8,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (77th release)
(Jun 8,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 8)
(Jun 8,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 7)
(Jun 8,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 8)
(Jun 8,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 pm, June 8)
(Jun 8,2011)Improvement of the working environment inside the Reactor Building, Unit 2, Fukushima Daiichi Nuclear Power Station
(Jun 7,2011)Receipt of evaluation by Nuclear and Industrial Safety Agency of Ministry of Economy, Trade and Industry concerning the report on offsite power supply security in nuclear power stations and so forth and an additional instruction document
(Jun 7,2011)Receipt of an instruction document about implementation of countermeasures against severe accidents in other nuclear power stations based on the accident in Fukushima Daiichi Nuclear Power Station
(Jun 7,2011)Submission of a report to Agency for Natural Resources and Energy of Ministry of Economics, Trade and Industry on the reporting obligation required by Clause 3 of Article 106 of Electricity Business Act
(Jun 7,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (76th release)
(Jun 7,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (74th release)
(Jun 7,2011)The result of the nuclide analysis of radioactive materials in the seawater collected in the offshore area of Ibaraki Prefecture (continued 4)
(Jun 7,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 7,2011)Improvement plan for the exact nuclide analysis at the site of Fukushima Daiichi Nuclear Power Station under instruction of NISA (Continued report 4)
(Jun 7,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 7)
(Jun 7,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 6)
(Jun 7,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 7)
(Jun 7,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 7)
(Jun 7,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 7)
(Jun 7,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 7)
(Jun 6,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 6)
(Jun 6,2011)Receipt of directive document "Regarding the response to the addition of opinions upon considered by NISA in relation to the report of the evaluation results on seismic safety of existing nuclear power reactor facilities etc. in light of the new Seismic Regulatory Guide based on the 2011 Tohoku District-Off the Pacific Ocean Earthquake (Additional Directive)"
(Jun 6,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (75th release)
(Jun 6,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 6)
(Jun 6,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 6)
(Jun 6,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (73rd release)
(Jun 6,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 5)
(Jun 6,2011)Outlook of Weekly Power Supply-Demand Balance of June
(Jun 6,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 6)
(Jun 6,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 6)
(Jun 5,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (74th release)
(Jun 5,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (72nd release)
(Jun 5,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 5)
(Jun 5,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 4)
(Jun 5,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 5)
(Jun 5,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 5)
(Jun 5,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 9:00 AM, June 5)
(Jun 5,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 5)
(Jun 4,2011)Submission of the Report on Transfer of High Level Radioactive Wastewater Accumulated in the Fukushima Daiichi Nuclear Power Station to the Centralized Radiation Waste Treatment Facility
(Jun 4,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 4)
(Jun 4,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (73rd release)
(Jun 4,2011)Detection of radioactive materials in the soil in Fukushima Daiichi Nuclear Power Station (15th release)
(Jun 4,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 4,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 3)
(Jun 4,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (71st release)
(Jun 4,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 4)
(Jun 4,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 4)
(Jun 4,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 4)
(Jun 4,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 4)
(Jun 3,2011)Report on countermeasures against outflow of radioactive water off the site near water intake of Unit 3 at Fukushima Daiichi Nuclear Power Station to NISA (2nd release)
(Jun 3,2011)Receipt of instruction documents with regard to inappropriate response required by electricity business act third clause of Article 106
(Jun 3,2011)Status of Evaluation Exposure Dose limits of TEPCO employees at Fukushima Daiichi Nuclear Power Station (Continued Releases)
(Jun 3,2011)Receipt of instruction documents with regard to the check considering the damage found in cylinder liners of emergency diesel generators of Monju", a fast-breeder reactor, of Japan Atomic Energy Agency (independent administrative institution)"
(Jun 3,2011)The results of nuclide analyses of radioactive materials in the ocean soil off the coast of Fukushima Daiichi Nuclear Power Station (continued report)
(Jun 3,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (72nd release)
(Jun 3,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 2)
(Jun 3,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (70th release)
(Jun 3,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 3)
(Jun 3,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 3)
(Jun 3,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 3)
(Jun 3,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 3)
(Jun 3,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 3)
(Jun 2,2011)Report on countermeasures against outflow of radioactive water off the site near water intake of Unit 3 at Fukushima Daiichi Nuclear Power Station to NISA
(Jun 2,2011)Receipt of collection of report on installment of treatment facility and storing facility of water including highly concentrated radioactive materials at Fukushima Daiichi Nuclear Power Station
(Jun 2,2011)Detection of Radioactive Materials from Subsurface Water near the Turbine Buildings of Fukushima Daiichi Nuclear Power Station
(Jun 2,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on June 1)
(Jun 2,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (71st release)
(Jun 2,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 2)
(Jun 2,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 2)
(Jun 2,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 2)
(Jun 2,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (69th release)
(Jun 2,2011)Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 2)
(Jun 2,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 2)
(Jun 2,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 9:00 AM, June 2)
(Jun 1,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 PM, June 1)
(Jun 1,2011)Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (70th release)
(Jun 1,2011)The results of nuclide analyses of radioactive materials in the air at the site of Fukushima Daiichi Nuclear Power Station (68th release)
(Jun 1,2011)The results of nuclide analyses of radioactive materials in seawater taken in areas near intake canal of Fukushima Daiichi Nuclear Power Station (for the data taken on May 31)
(Jun 1,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 1)
(Jun 1,2011)Receipt of written direction regarding the implementation of necessary measures for fire prevention in relation to overhang-type high-voltage breakers at nuclear power stations
(Jun 1,2011)Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 1)
(Jun 1,2011)Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 9:00 AM, June 1)
(Jun 1,2011)Correction of "Detection of Radioactive Materials from Seawater near Fukushima Daiichi Nuclear Power Station (69th release)"
(Jun 1,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, June 1)