Press Release (Feb 13,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, February 13)
*The updates are underlined
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
  explosion.
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 10:11 am on December 10, 2011, in addition to water injection from 
  water feeding system, we started water injection from piping of core 
  spray system to the reactor.
  The current water injection amount from the reactor feed water system is 
  approx.4.4 m3/h and that from the core spray system is approx. 1.8 m3/h.
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
  Primary Containment Vessel.
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
  in the spent fuel pool by an alternative cooling equipment of the Fuel 
  Pool Cooling and Filtering System. 
- On October 28, 2011, we completed installation of the cover for the 
  Reactor Building in order to contain dispersion of radioactive 
  substances.
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel.
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
  management system started.
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, 2011, an abnormal noise began 
  emanating from nearby Pressure Suppression Chamber and the pressure 
  within the chamber decreased. 
- At 10:10 am on March 26, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 2:59 pm on September 14, 2011, in addition to water injection from 
  feed water system, we started water injection from piping of core spray 
  system to the reactor. 
  Because the tendency of temperature rise at the bottom of PCV had been 
  accelerated since February 2, we increased the amount of water injected 
  to the reactor and continued monitoring the tendency of the temperature 
  fluctuation. Since the temperature increased slightly, at 3:30 pm on 
  February 12, 2012, we changed the water injection amount through the 
  reactor feed water system from approx. 7.2m3/h to 7.5m3/h and the water 
  injection amount through the core spray system from approx. 6.9m3/h to 
  9.9m3/h. At 5:01 pm on February 12, we sampled the gas of the gas 
  control system of Unit 2 Primary Containment Vessel. The density of 
  Xenon 135 at the entrance of the system was below the detection limit 
  (9.3X10-2Bq/cm3). Since it is below 1Bq/cm3, which is the threshold for 
  judging re-criticality, we confirmed the reactor didn't go re-critical. 
  After that, since we confirmed a change in the amount of water injection 
  to the Unit 2 nuclear reactor, at 7:30 pm on February 12, we changed the 
  amount of the water injection from the feed water system from 7.1m3/h to 
  7.5m3/h and water injection from the core spray system from 10.0m3/h to 
  9.9m3/h. Later we again confirmed a change in the amount of water 
  injection to the Unit 2 nuclear reactor, and at 9:50 am on February 13, 
  we changed the amount of the water injection from the feed water system 
  from 7.0m3/h to 7.5m3/h (water injection from the core spray system 
  maintained at 9.9m3/h).
  Currently, the temperature is approx. 93.3 °C (reference) as of 1:00 pm 
  on February 13. We are now investigating the measuring instrument. We 
  will continue to monitor the tendency of the temperature. 
  The current water injection amount from the reactor feed water system is 
  approx. 7.5 m3/h and that from the core spray system is approx. 9.9 m3/h.
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. At 1:29 pm on February 13, we started 
  injection of hydrazine [corrosion inhibitor].
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
  Primary Containment Vessel.
- At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas 
  control system started. 
- At 10:46 am on December 1, 2011, we started the nitrogen injection to 
  the Reactor Pressure Vessel.
- At 11:50 am on January 19, 2012, we started the operation of the spent 
  fuel pool desalting facility.
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14, 2011. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line.
- At 2:58 pm on September 1, 2011, we started water injection by core 
  spray system in addition to water injection by the reactor feed water 
  system piping arrangement.
  The current water injection amount from the reactor feed water system is 
  approx. 3 m3/h and that from the core spray system is approx. 6 m3/h.
  At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
  At 10:07 am on February 8, we stopped the operation of the secondary 
  cooling tower in order to prevent overcooling of alternative cooling 
  system of spent fuel pool of Unit 3. Afterward the temperature of the 
  water of the pool was increased so we operate the secondary cooling 
  tower at 10:08 am on February 13. 
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
  Since 9:50 am on February 10, we have conducted the work to add 
  flowmeters to the nitrogen injection line at the side of Primary 
  Containment Vessel of Unit 3 in order to improve the reliability of 
  nitrogen injection activity. During this period, due to this work, we 
  suspended the nitrogen injection task temporarily.
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel.
- At 3:18 pm on January 14, we started operation of the radioactive 
  material removal instrument for the spent fuel pool in Unit 3
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, 2011, we confirmed the explosive sound and 
  the sustained damage around the 5th floor rooftop area of Reactor 
  Building.
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
  installed Ion exchange equipment and started the operation of such 
  equipment.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal 
  System Pump in order to cool the spent fuel pool.
- At 2:45 pm on July 15, 2011, we started the operation of the original 
  Residual Heat Removal System (System B) by its original seawater pump.
- At 10:11 am on December 22, 2011, since we finished the recovery work of 
  seawater pump (System B) of equipment water cooling system, we made a 
  trial run. At 11:25 am on the same day, we confirmed no abnormalities 
  and restarted the operation.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal 
  System Pump of Unit 6 to cool down Spent Fuel Pool.
- At 2:33 pm on September 15, 2011, we started separately cooling the 
  reactor through the Residual Heat Removal System and the spent fuel pool 
  through Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage 
  inside PCV.
Others 
- At around 10:00 am on June 13, 2011, we started the operation of the 
  circulating seawater purification facility installed at the screen area 
  of Unit 2 and 3.
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
  Facility against the accumulated water. At 6:00 pm on July 2, we started 
  the circulating injection cooling to inject the water, which was treated 
  by the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
  by parallel operation of one line from the cesium adsorption instrument 
  to the decontamination instrument and the other treatment line of the 
  cesium adsorption instrument No.2.
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
  water brought from Unit 5 and 6 continually in order to prevent dust 
  scattering and potential fire outbreaks from the cut down trees.
- On October 28, 2011, we started installation of the water proof wall at 
  the sea side, in front of the existing shore protection, Units 1-4, in 
  order to contain marine pollution by underground water.
- At 12:25 pm on December 13, 2011, we started the re-circulating 
  operation of desalination facility (reverse osmosis membrane type) for 
  the purpose of suppression of condensed water after desalination 
  treatment.
- As accumulated water containing radioactive materials was found in the 
  trench between Process Main Building and Miscellaneous Solid Waste 
  Volume Reduction Treatment Building (High Temperature Incinerator 
  Building) in Centralized Radiation Waste Treatment Facility (December 18, 
  2011), inspection of other trenches in the site was commenced from 
  January 11.
- At 9:18 am on January 31, we started transfer of Sub-drain Water of Unit 
  6 to the temporary tank. We will conduct transferring to the temporary 
  tank appropriately.
- At 2:43 pm on February 10, we started to transfer accumulated water from 
  underground floor of turbine building of Unit 2 to centralized radiation 
  waste treatment facility (Miscellaneous Solid Waste Volume Reduction 
  Treatment Building [High Temperature Incinerator Building]).
- At 9:57 am on February 12, we started to transfer accumulated water in 
  the underground of turbine building of Unit 3 to the Centralized 
  Radiation Waste Treatment Facility (Process Main Building). 