Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of September 8)
We are announcing the status of major inspections and restoration works 
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station 
after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/ Restoration Status 

 ◇ Inspection and restoration completed between September 2 to September 
    8, 2011 
    (Completed on the following date) 

   - No notable activity during this week. 

 ◇ Inspection and restoration to be commenced between September 9 to 
    September 15, 2011 
    (To be commenced on the following date) 

   - No notable activity during this week. 

 ◇ Work Schedule of Major Inspection and Restoration from September 4 to 
    October 1, 2011 

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                               ...Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed 
after the Niigata-Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the 
 Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki 
 Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) 
 provides this announcement containing incidents information reported from 
 September 1 to September 7, 2011. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from September 1 to September 7, 2011>
Reports from September 1 to September 7, 2011
◇ Other Findings - Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades GI, GII, GIII; and non-graded) (including nonconformances related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
Other Findings
* By close reexamination of past nonconformance incidents, 1 of them is identified as not related to the Chuetsu-Oki Earthquake, so the total number of them has been corrected.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
          Earthquake (during 4 Weeks) (PDF 14.6KB)